Detailed Description of Executed Tasks

  1. Lay bare the steps
  2. Inspect the step 4×6 wood and decide if it can still be used or if it needs to be replaced
  3. Take out the steps that need to be replaced and cut new 6×4 wood (~4ft) and drill holes for rebar
    1. Second step would be to removed and be replaced and put two steps to make it easier for people to go up and down the staircase
  4. Place the 4×6 in right position supported by gravel and insert rebar with sledge hammer
  5. Paint untreated wood for the handrail
  6. Determine the length of the side piece of the box and cut it and use the l brackets to screw it in place
  7. Refill box with dirt from digging and gravel provided by Ranger Carol
  8. Dig post holes (~2ft) for new railings approximately every four feet where it matches with a 4×6 beam
  9. Put beam in hole and use spirit level to make sure it’s straight and screw it into the 4×6 for support
  10. Mix the Sika post mix and pour it quickly into each of the holes and wait for it to harden
  11. Replace broken post in the corner of the stairs
  12. Install missing handrail
  13. Determine height of the new handrail and cut posts
  14. Install handrails (painted untreated wood) onto the new posts: Cut to proper length and screw in place, paint edges
  15. Install horizontal balusters (treated wood): Cut to proper length and screw in place
  16. Place new side pillars in place of the missing side pillars